File #: 25-265    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 3/11/2025 In control: BOARD OF SUPERVISORS
On agenda: 3/18/2025 Final action:
Title: Consideration of Resolution Authorizing the Delegation of Authority to Public Services Director to approve and execute Change Orders for the Agreement for Construction of the Lake County Sheriff Administration Facility Renovation Project
Sponsors: Public Services
Attachments: 1. Signed Armory Change Order Delegation Draft Resolution

 

Memorandum

 

 

Date:                                          March 18, 2025

 

To:                                          The Honorable Eddie Crandell, Lake County Board of Supervisors

 

From:                                          Lars Ewing, Public Services Director

 

Subject:                     Consideration of Resolution Authorizing the Delegation of Authority to Public Services Director to approve and execute Change Orders for the Agreement for Construction of the Lake County Sheriff Administration Facility Renovation Project

 

Executive Summary:

 

As your Board is aware, the County is renovating the former National Guard Armory to serve as the new Lake County Sheriff Administration Center. On December 17, 2024, your Board approved an agreement for construction with Wright Contracting in the amount of $11,965,000. Construction is underway and progressing satisfactorily.

 

Construction projects often encounter unexpected conditions during execution, necessitating adjustments to the original scope of work defined in the contract to address these unforeseen issues. This is especially common in building renovation projects because of the nature of reusing existing infrastructure, even with detailed as built drawings and a comprehensive building inspection occurring during the design phase. While change orders are routine, solutions can require prompt approval to keep the project moving forward, on schedule, and within budget. The existing administrative approval process can prolong the construction schedule and potentially lead to contractor claims for project delays.

 

To minimize these concerns, the Public Contract Code (PCC) allows for the delegation of authority to a county official to approve and execute change orders, subject to Board-established monetary limits. Staff requests your Board’s delegation of authority to the Public Services Director to approve and execute contract change orders for the Lake County Sheriff Administration Facility Renovation Project, in accordance with PCC 20142, with the following highlights and limitations:

 

1)                     No change order executed through the delegated authority will exceed the $210,000 threshold defined in PCC 20142; and

2)                     The aggregate amount of change orders executed through the delegated authority will not exceed the threshold defined in PCC 20142, which for this project amounts to $610,750; and

3)                     The Public Services Director will present a quarterly report to your Board detailing the change orders approved under the delegated authority.

 

It is important to note that this action will not result in any new financial obligations beyond those previously approved by your Board for the project. Appropriations for the project already include a 10% contingency, and staff will ensure all change orders remain within appropriation limitations.

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost:________  Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                                           Business Process Efficiency                      Clear Lake                     

 

 

Recommended Action: Adopt Resolution Authorizing the Delegation of Authority to Public Services Director to approve and execute Change Orders for the Agreement for Construction of the Lake County Sheriff Administration Facility Renovation Project.