Legislation Details

File #: 26-0724    Version: 1 Name:
Type: Agreement Status: Agenda Ready
File created: 7/8/2026 In control: Lake County Sanitation District
On agenda: 7/21/2026 Final action:
Title: (Sitting as the Lake County Sanitation District Board of Directors) Approve Amendment No. 2 between the Lake County Sanitation District (LACOSAN) Northwest Wastewater Treatment Plant and Clearlake Oaks County Water District (CLOCWD) for the Acceptance of Effluent for Twenty-Five Years and authorize the Chair to sign
Sponsors: Special Districts, Lake County Sanitation District
Attachments: 1. Effluent Geyser Pipeline, 2. Geyser Pipeline, 3. Signed Revised Basin 2000 Pipeline revised Amendment 2 final 7.8.26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          July 21, 2026

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Robin Borre, Special Districts Administrator

 

Subject:                     (Sitting as the Lake County Sanitation District Board of Directors) Approve Amendment No. 2 between the Lake County Sanitation District (LACOSAN) Northwest Wastewater Treatment Plant and Clearlake Oaks County Water District (CLOCWD) for the Acceptance of Effluent for Twenty-Five Years and authorize the Chair to sign

 

Executive Summary:

 

LACOSAN and CLOCWD entered into the Agreement for the Acceptance of Effluent dated July 21, 1998, to transport effluent from Northwest Wastewater Treatment Plant to the Clearlake Oaks County Water Plant and to the Geyser Pipeline at the Southeast Wastewater Treatment Plant.  The original agreement was extended through Amendment No. 1.

 

Amendment No. 2 extends the term of the agreement for twenty-five years to coincide with the Geyser Agreement and updates some of the operation and maintenance section to include a mutual operation and maintenance understanding between LACOSAN - NW and CLOCWD. 

 

This amendment assures that LACOSAN and CLOCWD will be able to continue to dispose of the effluent from the two wastewater plants through the Geyser Pipeline.  This continued disposal method ensures that both plants continue to follow their NPDES permits and prevents possible issues that were experienced with the previous deposal method of land application.  This agreement further benefits both districts to ensure additional costs are not incurred to repair the land application systems.

 

Environmental was completed under the original project that installed the pipelines and pumping systems.  No additional environmental review is needed to extend the agreement.

 

All operation and maintenance expenses are included in the approved budget, and no additional funding is necessary to extend the agreement.

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ___0_____ Amount Budgeted: ____0____ Additional Requested: __0______ Future Annual Cost: __0_____

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: (Sitting as the Lake County Sanitation District Board of Directors) Approve Amendment No. 2 between the Lake County Sanitation District (LACOSAN) Northwest Wastewater Treatment Plant and Clearlake Oaks County Water District (CLOCWD) for the Acceptance of Effluent for Twenty-Five Years and authorize the Chair to sign.