Legislation Details

File #: 26-1123    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 11/10/2026 In control: BOARD OF SUPERVISORS
On agenda: 11/17/2026 Final action:
Title: Consideration of Change Order No. 1 to the contract for the Southshore Behavioral Health Expansion Project with Cupples and Sons Construction in the amount of $842,878.00 and 120 additional working days, for a revised contract amount of $5,308,287.09; and Authorize the Chair to sign.
Sponsors: Public Works , Behavioral Health Services
Attachments: 1. Agree_SouthshoreExpansion_BH, 2. CO# 001 - Demo Existing Interior Slab and Install new structural Mat Slab rv.1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

Date:                                          November 17, 2026

 

To:                                          The Honorable Brad Rasmussen, Lake County Board of Supervisors

 

From:                                          Stephen Carter, Interim Public Works Director

                                          Elise Jones, Behavioral Health Director

 

Subject:                      Consideration of Change Order No. 1 to the contract for the Southshore Behavioral Health Expansion Project with Cupples and Sons Construction in the amount of $842,878.00 and 120 additional working days, for a revised contract amount of $5,308,287.09 and 360 working days; and Authorize the Chair to sign.

 

Executive Summary:

 

As your Board is aware, the County is renovating and expanding the Southshore Behavioral Health Facility. Construction is approximately 20% complete and is on schedule for substantial completion date of September 2027 including this proposed change.

 

Change Order No. 1 addresses a construction defect and facility deuteration resulting in unforeseen field conditions. The Change Order included with this memorandum and specific information describing the changes can be found in the Change Order Document (CO# 001 - Demo Existing Interior Slab and Install New Structural Mat Slab)

 

It is important to note that the South Shore Behavioral Health Expansion Project is supported by a California Department of Health Care Services Bond Behavioral Health Continuum Infrastructure Program Round 1 grant and local matching funds. The County anticipates funding Change Order No. 1 within existing project resources.

 

Change Order No. 1 addresses a variety of issues with the existing building and delivers a structurally sound fully renovated facility backed by the projects structural engineer and contractor. Upon removal of the flooring a large crack running the full length of the building from East to West was uncovered. Through collaboration with the Contractor, Geotechnical and Structural engineers it was determined that expansive soil conditions allowed the building perimeter to settle as much as 1.75 inches in some areas causing alignment issues and the interior slab to fail. To remedy the failure and prevent future settling, a new structural 12” thick foundational mat slab will be installed and connected to the existing perimeter foundation. 

 

If not budgeted, fill in the blanks below only:

Estimated Cost:________  Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                          ☐ Not applicable

☒ Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

☐ Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

☐ For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

☐ Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                               ☐ Not applicable

☒ Well-being of Residents                                          ☒ Public Safety                                                               ☒ Disaster Prevention, Preparedness, Recovery                     

☐ Economic Development                                          ☒ Infrastructure                                                               ☒ County Workforce                     

☐ Community Collaboration                     ☒ Business Process Efficiency                     ☐ Clear Lake                     

 

Recommended Action: Approve Change Order No. 1 to the contract with Cupples & Sons Construction, in the amount of $842,878.00 and 120 additional working days, for a revised contract amount of $5,308,287.09, and 360 working days, and authorize the Chair to sign.