File #: 24-1245    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 12/5/2024 In control: BOARD OF SUPERVISORS
On agenda: 12/17/2024 Final action:
Title: Consideration of (a) Contract Change Order No. 4 to the construction contract between Lake County and Argonaut Constructors, Inc. for the construction of the Middletown Multi-Use Path Project (State Project No. ATPL-5914(102)) in the amount of $8,032.66, increasing the contract amount from $1,408,959.29 to a new contract amount of $1,416,991.95; (b) Resolution Accepting the Work of the Middletown Multi-Use Project (State Project No. ATPL-5914(102)) ; and (c) Direction to the Director of Public Works to file the Notice of Completion with the County of Lake Recorder’s Office
Sponsors: Public Works
Attachments: 1. Middletown Multi-Use Path - Contract Change Order No. 4, 2. ResMiddletownMultiuseTrail, 3. Middletown Multi-Use Path Project - Notice of Completion

Memorandum

 

 

Date:                                          December 17, 2024

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Glen March, Public Works Director

                                          Pablo Pantaleon, Assistant Engineer

 

Subject:                     Consideration of (a) Contract Change Order No. 4 to the construction contract between Lake County and Argonaut Constructors, Inc. for the construction of the Middletown Multi-Use Path Project (State Project No. ATPL-5914(102)) in the amount of $8,032.66, increasing the contract amount from $1,408,959.29 to a new contract amount of $1,416,991.95; (b)  Resolution Accepting the Work of the Middletown Multi-Use Project (State Project No. ATPL-5914(102)) ; and (c) Direction to the Director of Public Works to file the Notice of Completion with the County of Lake Recorder’s Office

 

Executive Summary:

 

On May 24, 2022, the Board executed a construction contract between Lake County (County) and Argonaut Constructors, Inc. (Contractor) in the amount of $1,117,449.60, for construction of the Middletown Multi-Use Path Project (Project).

 

Staff prepared Contract Change Order (CCO) No. 4, in the amount of $8,032.66. CCO No.4 will increase the current contract amount of $1,408,959.29 to the new contract amount of $1,416,991.95. CCO No. 4 (1) adjusts the estimated quantity of certain bid items shown on the bid form to the actual final in-place quantities; (2) compensates Contractor for placing additional hot mix asphalt; modifying five bollards; and replacing one bollard.  CCO No. 4 and the associated change order memorandum are attached.

 

On November 15, 2024, the work was completed to the satisfaction of the Director of Public Works and Caltrans staff.  The Director of Public Works recommends the Board of Supervisors accept the work.

 

The Director of Public Works recommends the filing of the Notice of Completion, which decreases the time for the release of retention from 90 days after the completion of the work to 30 days after filing the notice of completion. The Notice of Completion is attached.

 

A resolution accepting the work of the Middletown Multi-Use Path Project (State Project No. ATPL-5914(102)) and directing the Director of Public Works to file the Notice of Completion with the County of Lake’s Recorder’s Office is attached.

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

 

The Director of Public Works recommends:

 

(a) Approve Contract Change Order no. 4 to the construction contract between Lake County and Argonaut Constructors, Inc. for the construction of the Middletown Multi-Use Path Project (State Project No. ATPL-5914(102)) in the amount of $8,032.66, increasing the contract amount from $1,408,959.29 to a new contract amount of $1,416,991.95 and authorize the Chair to sign the Change Order.

 

(b) Adopt Resolution accepting the work of the Middletown Multi-Use Path Project (State Project No. ATPL-5914(102)).

 

(c) Direct the Director of Public Works to file the Notice of Completion with the County of Lake Recorder’s Office