Legislation Details

File #: 20-33    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 1/10/2020 In control: BOARD OF SUPERVISORS
On agenda: 1/28/2020 Final action:
Title: Approve Plans and Specifications for the Clayton Creek Road at Clayton Creek Bridge Replacement Project; Bid No. 20-02, Federal Project No: BRLO-5914(077)
Sponsors: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          January 28, 2020

 

To:                                          The Honorable Moke Simon, Chair, Lake County Board of Supervisors

                                          

From:                                          Scott De Leon, Public Works director

                     

Subject:                     Approve Plans and Specifications for the Clayton Creek Road at Clayton Creek Bridge Replacement Project; Bid No. 20-02, Federal Project No: BRLO-5914(077)

 

Executive Summary: (include fiscal and staffing impact narrative):

The Plans and Specifications for the Clayton Creek Road at Clayton Creek Bridge Replacement Project are complete and a copy has been filed with the Clerk of the Board.

 

The construction estimate is approximately $2,002,000.

 

The California Department of Transportation (Caltrans) provides funds to eligible projects through the Highway Bridge Program (HBP). Therefore, this project is 100% funded for construction with Federal funds.

 

Staff recommends that the Board of Supervisors approve the Plans and Specifications and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans.

 

Note:  To minimize reproduction costs, the original documents are attached to the Clerk’s copy of the original cover memo and only a copy of this memo is furnished to each individual board member                                 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: $2,002,000.00_ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                          ☐ Not applicable

☒ Well-being of Residents                                          ☒ Public Safety                                                               ☒ Infrastructure                                          ☐ Technology Upgrades

☐ Economic Development                                          ☐ Disaster Recovery                                          ☐ County Workforce                     ☐ Revenue Generation

☐ Community Collaboration                     ☐ Business Process Efficiency                     ☐ Clear Lake                                          ☐ Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action: Approve the Plans and Specifications and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans.