Title: Approve Contract Change Order No. 3 to the contract for Zara Construction, Inc. for the Kelseyville Sidewalks Project, County Project No. 251335, Federal Project No. HIPL-5914(133), increasing the contract amount by $2,121.88 for a total revised contract amount of $813,734.88 and authorize Chair to sign
Sponsors: Public Works
Attachments: 1. CCO #3 - Balancing of Final In-Place Quantities - Signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          July 28, 2026

 

To:                                          The Honorable Brad Rasmussen, Chair, Lake County Board of Supervisors

 

From:                                          Lars Ewing, Public Works Director

 

Subject:                     Approve Contract Change Order No. 3 to the contract for Zara Construction, Inc. for the Kelseyville Sidewalks Project, County Project No. 251335, Federal Project No. HIPL-5914(133), increasing the contract amount by $2,121.88 for a total revised contract amount of $813,734.88 and authorize the Chair to sign

 

Executive Summary:

 

On December 2, 2025, your Board entered into a contract with Zara Construction Inc. for the Kelseyville Sidewalks Project on Konocti Rd in Kelseyville, CA.

 

Attached for the Board’s consideration is Contract Change Order No. 3 (CCO 3) for the Kelseyville Sidewalks Project. CCO 3 addresses the balancing of all contract bid items to reflect actual in-place quantities.  Funding for this project is through the Federal Highways Infrastructure Program using Congressional Directed Spending secured from Congressman Mike Thompson, as well as County SB1 funds.  Sufficient appropriations are available to cover the additional construction costs associated with this change order.

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

 

Approve Contract Change Order No. 3 for the Kelseyville Sidewalks Project, County Project No. 251335, Federal Project No. HIPL-5914(133), increasing the contract amount by $2,121.88 for a revised total contract amount of $813,734.88, and authorize the Chair to sign the change order.