Title: (a) Waive the formal bidding process pursuant to Lake County Code Section 38.2, as it is not in the public interest due to the unique nature of goods or services; and (b) Approve the Agreement between the County of Lake and Resource Development Associates for the Community Planning Program (CPP) Process for Fiscal Year 2020-21 for a contract maximum of $61,675 and authorize the Board Chair to sign the Agreement
Sponsors: Behavioral Health Services
Attachments: 1. RDA CPP FY 20-21
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          October 6, 2020                     

 

To:                                          The Honorable Moke Simon, Chair, Lake County Board of Supervisors

 

From:                                          Todd Metcalf, M.P.A.

 

                                          Behavioral Health Services Director

                     

Subject:                     (a) Waive the formal bidding process pursuant to Lake County Code Section 38.2, as it is not in the public interest due to the unique nature of goods or services; and (b) Approve the Agreement between the County of Lake and Resource Development Associates for the Community Planning Program (CPP) Process for Fiscal Year 2020-21 for a contract maximum of $61,675 and authorize the Board Chair to sign the Agreement.

 

Executive Summary: Lake County Behavioral Health Services (LCBHS) has previously contracted with the contractor for assistance with MHSA three year plans and updates; therefore, LCBHS is willing to contract with RDA in order to receive their assistance with the Community Planning Program process for Fiscal Year 2020-21. LCBHS is requesting approval of the Agreement with Resource Development Associates for the Community Planning Program process for Fiscal Year 2019-20 for a contract maximum of $61,675.

                                                      

 

If not budgeted, fill in the blanks below only:

Estimated Cost: $61,675 Amount Budgeted: $61,675  Additional Requested: $0  Future Annual Cost: TBD 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                          ☐ Not applicable

☒ Well-being of Residents                                          ☐ Public Safety                                                               ☐ Infrastructure                                          ☐ Technology Upgrades

☐ Economic Development                                          ☐ Disaster Recovery                                          ☐ County Workforce                     ☐ Revenue Generation

☐ Community Collaboration                     ☐ Business Process Efficiency                     ☐ Clear Lake                                          ☐ Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested? 38.2

How long has Agreement been in place?  Ongoing

When was purchase last rebid? N/A

Reason for request to waive bid? Unique Nature of Goods/Services

 

Recommended Action:                     (a) Waive the formal bidding process pursuant to Lake County Code Section 38.2, as it is not in the public interest due to the unique nature of goods or services; and (b) Approve the Agreement between the County of Lake and Resource Development Associates for the Community Planning Program (CPP) Process for Fiscal Year 2020-21 for a contract maximum of $61,675 and authorize the Board Chair to sign the Agreement.