Legislation Details

File #: 26-0459    Version: 1 Name:
Type: Agreement Status: Agenda Ready
File created: 4/29/2026 In control: BOARD OF SUPERVISORS
On agenda: 5/12/2026 Final action:
Title: Approve Amendment Eight to the Agreement between the County of Lake and Consor Engineering for Engineering Services for Replacement of Clover Creek Bridge at First Street (14C-0015) for an increase of $242,200 and Authorize the Chair to Sign
Sponsors: Public Works
Attachments: 1. Amendment 8 - EngSvs Consor for Replacement of Clover Crk Bridge at First St 14C-0015, 2. Agreement - Clover Creek at First St - Fully Executed, 3. Amendment 1 - Clover Creek at First St - Fully Executed, 4. Amendment 2 - Clover Creek at First St - Fully Executed, 5. Amendment 3 - Clover Creek at First St - Fully Executed, 6. Amendment 4 - Clover Creek at First St - Fully Executed, 7. Amendment 5 - Clover Creek at First St - Fully Executed, 8. Amendment 6 - Clover Creek at First St - Fully Executed, 9. Amendment 7 - Clover Creek at First St - Fully Executed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          May 12, 2026

 

To:                                          The Honorable Brad Rasmussen, Chair, Lake County Board of Supervisors

 

From:                                          Lars Ewing, Public Works Director

 

Subject:                     Approve Amendment Eight to the Agreement between the County of Lake and Consor Engineering for Engineering Services for Replacement of Clover Creek Bridge at First Street (14C-0015) for an increase of $242,200 and Authorize the Chair to Sign

 

Executive Summary:

 

On February 28, 2017, the County of Lake entered into an agreement with Quincy Engineering to provide preliminary and final design, environmental services, right of way, bidding and construction assistance services for the project to replace the Clover Creek Bridge at First Street (14C-0015).  On December 20, 2022, Quincy Engineering was acquired by Consor Engineering, and the project agreement between the County and Quincy was assigned to Consor.

 

The amendment incorporates additional design services to revise the foundation design and address Caltrans comments to mitigate for weak/soft soil conditions supporting the new structure, changes resulting from right-of-way negotiations, and changes in approach to stormwater treatment compliance.  The amendment also incorporates additional coordination with the permitting agencies to verify the permits are still valid after design changes, and to obtain revised permits if necessary.

 

Public Works staff reviewed the proposed scope of work consulted with Caltrans local assistance to confirm that the work is justified, and prepared the attached amendment for your Board’s consideration. The project is fully funded through the federal Highway Bridge Program.

 

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action:  Approve Amendment Eight to the Agreement between the County of Lake and Consor Engineering for Engineering Services for Replacement of Clover Creek Bridge at First Street (14C-0015) for an increase of $242,200 and Authorize the Chair to Sign.