Date:                                          May 9, 2022

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Susan Parker, County Administrative Officer

                                          Stephen Carter, Assistant County Administrative Officer

                                          Benjamin Rickelman, Deputy County Administrative Officer

                                          Matthew Rothstein, Deputy County Administrative Officer

 

Subject:                     Consideration of an Update on the Broadband Action Planning Process, by CBG Communications, Inc.

 

Executive Summary:

As you will recall, on December 20, 2022, your Board adopted an Agreement with CBG Communications, Inc., for Broadband Action Plan Consulting Services, in the not-to-exceed amount of $245,000.  Tom Robinson, CBG’s Chief Executive Officer, appeared before your Board on that date:

<https://www.youtube.com/watch?v=C91AzJsY0SE>

 

A summary of CBG’s actions and progress to date is attached to this Memo, and Mr. Robinson will again be present via Zoom, to answer your questions, and discuss next steps.  Administration staff will likewise be available for this item, and look forward to any discussion and/or direction.

 

Background

On July 19, 2022, your Board approved allocation of up to $300,000 to fund an Agreement for a Broadband Action Plan Consultant.  RFP 22-32 was issued August 5, 2022, with a submission deadline of Thursday, September 15, 2022.  Six Proposals were ultimately received and determined to be complete.  A Consultant Selection Panel was convened Tuesday, October 11, 2022, and the Panel conducted follow-up interviews Thursday, October 27, 2022, with the two provisionally top-ranked candidates.  As a result of that process, CBG Communications, Inc., was identified as the most suitable firm to conduct the Scope of Work envisioned by RFP 22-32.  Your Board awarded a Contract to CBG, in the not-to-exceed amount of $245,000, Tuesday, December 20, 2022.  The CBG team has been working in earnest in the months since, and the attached document describes their progress, to date.

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action:  Informational report.  Consider direction to staff.