Legislation Details

File #: 26-0492    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 5/6/2026 In control: Lake County Watershed Protection District
On agenda: 6/9/2026 Final action:
Title: 2:00 P.M. - (Sitting as the Lake County Watershed Protection District Board of Directors) Consideration of Discussion from the Middle Creek Restoration Project Committee on the Middle Creek Restoration Project (MCRP) - Status Update and Direction on Property Acquisition Strategies
Sponsors: Water Resources, Lake County Watershed Protection District
Attachments: 1. Letter from MCPC to BOS_08.04.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          June 9, 2026                     

 

To:                     The Honorable Lake County Board of Supervisors, serving as the Directors of the Lake County Watershed Protection District

 

From:                     Dr. Pawan Upadhyay, Director, and Michael Bedar, Program Coordinator, Water Resources Department

                     

Subject:                     Consideration of Discussion from the Middle Creek Restoration Project Committee on the Middle Creek Restoration Project (MCRP) - Status Update and Direction on Property Acquisition Strategies

 

 

Executive Summary:

 

The Lake County Watershed Protection District and the Middle Creek Restoration Project (MCRP) Committee request that the Board of Supervisors receive an update on the Middle Creek Flood Damage Reduction and Ecosystem Restoration Project and provide direction on key next steps related to property acquisition, funding strategy, and coordination with state and federal partners.

 

The MCRP Committee includes Supervisor Crandell, Supervisor Sabatier, Merry Jo Velasquez, Harry Lyons, and Water Resources Director Dr. Pawan Upadhyay.

 

The Middle Creek Restoration Project is a multi-benefit initiative aimed at reducing flood risk in the Upper Lake area, restoring wetland and habitat conditions, and improving water quality in Clear Lake. Recent scientific analysis indicates that wetland restoration in this area could reduce sediment and nutrient loading to Clear Lake by approximately 36% or more, with additional reductions achievable through vegetation establishment. These outcomes are critical to long-term watershed health and harmful algal bloom (HAB) mitigation.

 

The project continues to make substantial progress, with approximately 79% of project properties acquired, in process, or tribal-owned, reflecting strong forward momentum. However, key challenges remain, including acquisition of unwilling properties, potential funding gaps, and evolving requirements from the U.S. Army Corps of Engineers (USACE).

 

Staff is seeking Board direction on strategies to address remaining acquisition challenges, including consideration of enhanced negotiations and potential use of eminent domain, as well as guidance on advancing project design and interagency coordination.

                                                      

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted:  __ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested? NA

How long has Agreement been in place?

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action: 1) Provide direction on property acquisition strategy, including approach for unwilling sellers, and overall project advancement.

                     2) Accept the ‘Middle Creek Project Status Update and Request for Board Action on the non-willing sellers’ Letter