File #: 24-580    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/14/2024 In control: BOARD OF SUPERVISORS
On agenda: 5/21/2024 Final action:
Title: 11:00 A.M. - a) Consideration and Presentation of the Soda Bay Corridor Evacuation Route Planning and Maintenance Grant Project and; b) Consideration and Approval of the Soda Bay Corridor Evacuation Plan prepared by Headway Transportation Consultants
Sponsors: Public Works
Attachments: 1. Final Soda Bay Evacuation Plan

Memorandum

 

 

Date:                                          May 21, 2024

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

 

a)                     Subject:                     Presentation of the Soda Bay Corridor Evacuation Route Planning and Maintenance Grant Project and

b)                     Consideration and approval of the Soda Bay Corridor Evacuation Plan prepared by Headway Transportation Consultants

 

 

Executive Summary:

 

As your Board is aware, the Department of Public Works, together with the County Chief Climate Resiliency Officer, representatives from the Konocti Fire Safe Council and Homeowners Association’s from Buckingham, Riviera Heights, Riviera West, and Kelseyville Riviera, Headway Transportation, and the Clear Lake Environmental Research Center (CLERC) recently completed the Soda Bay Corridor Evacuation Route Planning and Maintenance Project.  This project was funded through a grant provided by the California State Firesafe Council and CalFire.  Today’s item is for your Board and the public to receive a presentation on the project and its accomplishments.  Additionally, the Board will also receive a presentation on the Evacuation Plan prepared by Headway Transportation Consultants, with an action item to formally approve the Plan.

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

 

Staff recommends that the Board of Supervisors Approve the Evacuation Plan for the Soda Bay Corridor and Surrounding Communities dated March 15, 2024, as prepared by Headway Transportation.