Title: Approve Amendment Seven to the Agreement between the County of Lake and Quincy Engineering for Engineering Services for Replacement of St. Helena Creek Bridge at Wardlaw Street (14C-0035) and Rehabilitation of Cooper Creek Bridge at Witter Springs Road (14C-0102) in Lake County, CA in the amount of $80,000 and Authorize the Chair to sign.
Sponsors: Public Works
Attachments: 1. CONSOR Amdendment 7 - Two Bridges, 2. Agreement - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed, 3. Amendment 1 - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed Re-Signed, 4. Amendment 2 - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed, 5. Amendment 3 - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed, 6. Amendment 4 - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed, 7. Amendment 5 - St Helena at Wardlaw & Cooper at Witter 102 - Fully Executed, 8. St Helena at Wardlaw & Cooper at Witter 102 - Amendment 6 - Term Extension
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          May 20, 2025

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Glen March, Public Works Director

                                          David Bingham, Capital Project Manager

 

 

Subject:                     Approve Amendment Seven to the Agreement between the County of Lake and Quincy Engineering for Engineering Services for Replacement of St. Helena Creek Bridge at Wardlaw Street (14C-0035) and Rehabilitation of Cooper Creek Bridge at Witter Springs Road (14C-0102) in Lake County, CA in the Amount of $80,000 and Authorize the Chair to sign.

 

Executive Summary:

 

On June 2, 2015, the County of Lake entered into an agreement with Quincy Engineering to provide preliminary and final design, environmental services, right of way, bidding, and construction assistance services for the replacement of the St. Helena Creek Bridge at Wardlaw Street (14C-0035) and the rehabilitation of the Cooper Creek Bridge at Witter Springs Road (14C-0102).  On December 20, 2022, Quincy Engineering was acquired by Consor North America and the agreement between the County of Lake and Quincy Engineering was assigned to the parent company, Consor North America.

 

This amendment request is for contract changes to complete the NEPA and CEQA activities for the Cooper Creek Bridge at Witter Springs Road (14C-0102) Rehabilitation Project. The following changes have been identified that will require a contract amendment:

 

1.                     Revisions to the Type Selection Memorandum.  Consor prepared a Type Selection Memorandum that received preliminary concurrence from Caltrans.  Revisions to the memo were not included in the original scope of work.  Caltrans now requires an update to the Type Selection Memorandum.

 

2.                     Changes to the Area of Potential Effects (APE).  Additional discoveries were made from Extended Phase 1 Cultural Studies required for the project. The APE limits were modified in 2018, after some of the field work and technical studies had been performed. Additional field work and revisions to the technical studies are now required to update the latest field conditions.

 

3.                     Additional environmental technical studies required by Caltrans.  Caltrans has new requirements for studies for Cultural Resources since the last amendment was written. 

 

4.                     Initial Site Assessment for Hazardous Waste.  The original scope of work included a Preliminary Environmental Assessment. Based on the findings of the preliminary environmental assessment, an Initial Site Assessment is required for the project. 

 

Attached are a detailed scope of work and cost proposal for the contract amendment. Staff reviewed Consor’s request for Amendment 7, consulted with Caltrans, and found the request justifiable. Amendment Seven increases the engineering cost for this project by $80,000.00.

 

 

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

 

 

The Public Works Director recommends that the Board of Supervisors approve Amendment Seven to the Agreement for Engineering Services for Replacement of St. Helena Creek Bridge at Wardlaw Street (14C-0035) and Rehabilitation of Cooper Creek Bridge at Witter Springs Road (14C-0102) with Consor and authorize the Chairman to execute said Amendment.