File #: 24-1246    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 12/5/2024 In control: BOARD OF SUPERVISORS
On agenda: 12/17/2024 Final action:
Title: Consideration of (a) Contract Change Order No. 1 to the construction contract between Lake County and Lamon Construction Co., Inc. for the construction of the Nice-Lucerne Cutoff Asphalt Rehabilitation Project (State Project No. CRARPL-5914(126)) in the amount of $266.41, increasing the contract amount from $210,215.20 to a new contract amount of $210,481.61; (b) Resolution Accepting the work of the Nice-Lucerne Cutoff Asphalt Rehabilitation Project (State Project No. CRARPL-5914(126)); and (c) Direction to the Public Works DIrector to file the Notice of Completion with the County of Lake Recorder’s Office
Sponsors: Public Works
Attachments: 1. Nice-Lucerne Cutoff Asphalt Rehabilitation - Contract Change Order No. 1, 2. ResNLCutoff, 3. Nice-Lucerne - Notice of Completion
Memorandum


Date: December 17, 2024

To: The Honorable Lake County Board of Supervisors

From: Glen March, Public Works Director
Estrella Munoz, Assistant Engineer

Subject: Consideration of (a) Contract Change Order No. 1 to the construction contract between Lake County and Lamon Construction Co., Inc. for the construction of the Nice-Lucerne Cutoff Asphalt Rehabilitation Project (State Project No. CRARPL-5914(126)) in the amount of $266.41, increasing the contract amount from $210,215.20 to a new contract amount of $210,481.61; (b) Resolution Accepting the work of the Nice-Lucerne Cutoff Asphalt Rehabilitation Project (State Project No. CRARPL-5914(126)); and (c) Direction to the Public Works Director to file the Notice of Completion with the County of Lake Recorder's Office

Executive Summary:

On May 7, 2024, the Board executed a construction contract between Lake County (County) and Lamon Construction Co., Inc. (Contractor) in the amount of $210,215.20, for construction of the Nice-Lucerne Cutoff Asphalt Rehabilitation Project (Project).

Staff prepared Contract Change Order (CCO) No. 1, in the amount of $266.41. CCO No.1 will increase the current contract amount of $210,215.20 to the new contract amount of $210,481.61. CCO No. 1 adjusts the estimated quantity of certain bid items shown on the bid form to the actual final in-place quantities. CCO No. 1 and the associated change order memorandum are attached.

On November 18, 2024, the work was completed to the satisfaction of the Director of Public Works and Caltrans staff. The Director of Public Works recommends the Board of Supervisors accept the work.

The Director of Public Works recommends the filing of the Notice of Completion, which decreases the time for the release of retention from 90 days after the completion of the work to 30 days after filing the notice of completion. The Notice of Completion is attached.

A resolution accepting the work of the Nice-Lucerne Cutoff Asphalt Rehabilitation Pat...