File #: 24-1152    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 10/30/2024 In control: BOARD OF SUPERVISORS
On agenda: 12/3/2024 Final action:
Title: Accept the Offers of Dedication and Adopt the Resolution Approving the Final Subdivision Map - Valley Oaks Subdivision Village PDC II Phase I
Sponsors: Public Works
Attachments: 1. Resolution-ValleyOaks, 2. CDD PlanningCommissionMemo, 3. Maps-ValleyOaksPDCIIPhaseI
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Memorandum


Date: December 3, 2024

To: The Honorable Lake County Board of Supervisors

From: Glen March, Public Works Director
Vance Ricks, County Surveyor

Subject: Accept the Offers of Dedication and Adopt the Resolution Approving the Final Subdivision Map - Valley Oaks Subdivision Village PDC II Phase I

Executive Summary:

On October 24, 2024, the Planning Commission reviewed the final map for this project and found it to be in conformance with the approved tentative map. Per the attached Planning Commission memo, the subdivider has met all the requirements of the subdivision ordinance and all the tentative map conditions.

The Department of Public Works recommends acceptance of the offer of dedication of Oak Meadow Drive as a public roadway and public utility easements, along with the public utility easements and public sidewalk easement, drainage easements and Parcel G, all as shown on the subdivision map, but not for maintenance purposes.

Offsite dedications for Emergency Vehicle Access easements, drainage easements, public utility easement and roadway easement shown as Oak Meadow Drive, and Roadway dedication along Hartmann Road will also be recorded concurrently with the final subdivision map.


If not budgeted, fill in the blanks below only:
Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________

Purchasing Considerations (check all that apply): ? Not applicable
? Fully Article X.- and/or Consultant Selection Policy-Compliant (describe process undertaken in "Executive Summary")
? Section 2-38 Exemption from Competitive Bidding (rationale in "Executive Summary," attach documentation, as needed)
? For Technology Purchases: Vetted and Supported by the Technology Governance Committee ("Yes," if checked)
? Other (Please describe in Executive Summary)