Memorandum
Date: January 18, 2023
To: The Honorable Lake County Board of Supervisors
From: Scott De Leon, Public Works Director
Subject: Approve Plans and Specifications for the Bartlett Springs Road at Bartlett Creek Bridge Replacement Project; Bid No. 23-02, Federal Project No: BRLO-5914(111)
Executive Summary:
The Plans and Specifications for the Bartlett Springs Road at Bartlett Creek Bridge Replacement Project are complete and a copy has been filed with the Clerk of the Board.
The construction estimate is approximately $1,917,000.
The California Department of Transportation (Caltrans) provides funds to eligible projects through the Highway Bridge Program (HBP). Therefore, this project is 100% funded for construction with Federal funds.
Note: To minimize reproduction costs, the original documents are attached to the Clerk's copy of the original cover memo and only a copy of this memo is furnished to each individual board member
If not budgeted, fill in the blanks below only:
Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________
Purchasing Considerations (check all that apply): ? Not applicable
? Fully Article X.- and/or Consultant Selection Policy-Compliant (describe process undertaken in "Executive Summary")
? Section 2-38 Exemption from Competitive Bidding (rationale in "Executive Summary," attach documentation, as needed)
? For Technology Purchases: Vetted and Supported by the Technology Governance Committee ("Yes," if checked)
? Other (Please describe in Executive Summary)
Consistency with Vision 2028 (check all that apply): ? Not applicable
? Well-being of Residents ? Public Safety ? Disaster Prevention, Preparedness, Recovery
? Economic Development ? Infrastructure ? County Workforce
? Community Collaboration ? Business Process Efficiency ? Clear Lake
Recommended Action:
Staff recommends that the Board of Supervisors approve the Plans and Specifications a...