Title: Consideration of Change Order No. 1 to the Agreement with Rege Construction for the Eastlake Sanitary Landfill Phase One Cell Expansion Project, Bid No. 23-32, for an increase of $1,054,248.00 and a revised contract amount of $6,215,911.00, and authorize the Chair to sign
Sponsors: Public Services
Attachments: 1. BID 23-32 CO#1
Memorandum


Date: June 18, 2024

To: The Honorable Bruno Sabatier, Chair, Lake County Board of Supervisors

From: Lars Ewing, Public Services Director

Subject: Consideration of Change Order No. 1 to the Agreement with Rege Construction, Inc. for the Eastlake Sanitary Landfill Phase One Cell Expansion Project, Bid No. 23-32, for an increase of $1,054,248.00 and a revised contract amount of $6,215,911.00

Summary

Attached for the Board's review and approval is Change Order No. 1 to the Agreement with Rege Construction, Inc. for the Eastlake Sanitary Landfill Phase One Cell Expansion Project.

This change order includes scope, schedule, and cost increases to the contract in response to landfill slope stability comments from the Central Valley Regional Water Quality Control Board. The scope and cost increases are the result of the addition of a newly designed underdrain system along the entire cell floor area, and enhanced perimeter storm drain erosion control measures. The change order also includes contract scope and cost deductions that become obsolete because of the proposed modifications, as well as added contract working days.

The result is an increase of $1,054,248.00 to the original contract amount for a revised contract total of $6,215,911.00. Sufficient FY 23-24 capital appropriations are included in Budget Unit 4121, Integrated Waste Management, for costs that will be incurred this fiscal year. The FY 24-25 budget will include appropriations for costs incurred next fiscal year.


If not budgeted, fill in the blanks below only:
Estimated Cost:________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________

Purchasing Considerations (check all that apply): ? Not applicable
? Fully Article X.- and/or Consultant Selection Policy-Compliant (describe process undertaken in "Executive Summary")
? Section 2-38 Exemption from Competitive Bidding (rationale in "Executive Summary," attach documentation, as needed)
? For Technol...