Memorandum
Date: October 6, 2026
To: The Honorable Brad Rasmussen, Chair, Lake County Board of Supervisors
From: Stephen Carter, Interim Public Works Director
Presented by Scott Hornung, Deputy Public Works Director – Engineering & Capital Projects
Subject: A) Consideration of Update on the South Main Street and Soda Bay Road Corridor Improvement Project; and B) Consideration of Plans and Specifications for the South Main Street and Soda Bay Road Corridor Improvement Project, and Authorize the Public Works Director to Advertise for Bids
Executive Summary:
The Public Works Department is nearing completion of the pre-construction efforts for Phase 1 of the South Main Street and Soda Bay Road Corridor Improvement Project and requests authorization to advertise the project for construction bids.
The overall project (collectively Phase 1 and Phase 2) extends approximately 1.25 miles, from the Lakeport city limits along South Main Street to the intersection with State Highway 175 and Soda Bay Road, then south on Soda Bay Road toward Manning Creek. The project will reconstruct and widen the roadway with two 12-foot travel lanes, a continuous 12-foot center turn lane, and 8-foot paved shoulders/Class II bicycle lanes; improve drainage; install water infrastructure; and relocate existing overhead utilities underground.
Phase 1 includes the full length of South Main Street within the project limits and a short portion of Soda Bay Road immediately south of the intersection with State Highway 175. The remaining Soda Bay Road improvements will require a future phase as additional funding becomes available.
Phase 1 includes three major infrastructure components:
Component
Current Estimate
Funding Responsibility
County roadway and drainage improvements
$9.0 million
Transportation funding
Underground dry utility joint trench
$4.45 million
Utilities
Water/sewer improvements
$4.3 million
County & City of Lakeport
The roadway project is supported by...