Legislation Details

File #: 26-0930    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 9/15/2026 In control: BOARD OF SUPERVISORS
On agenda: 9/22/2026 Final action:
Title: (Sitting as the Lake County Watershed Protection District Board of Directors) Approve a $200,000 Engineering Advance to Pacific Gas and Electric Company (PG&E) for Preliminary Engineering Associated with Transmission Tower Modifications for the Middle Creek Restoration Project and Authorize the Water Resources Director to Sign Related Documents
Sponsors: Water Resources, Lake County Watershed Protection District
Attachments: 1. Middle Creek Restoration-Dist. Deposit Ltr Nov.2019
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Memorandum


Date: September 22, 2026

To: The Honorable Lake County Board of Supervisors

From: Dr. Pawan Upadhyay, Water Resources Director and
Michael Bedar, Water Resources Program Coordinator

Subject: (Sitting as the Lake County Watershed Protection District Board of Directors) Approve a $200,000 Engineering Advance to Pacific Gas and Electric Company (PG&E) for Preliminary Engineering Associated with Transmission Tower Modifications for the Middle Creek Restoration Project and Authorize the Water Resources Director to Sign Related Documents

Executive Summary:

The Middle Creek Restoration Project requires modification and/or relocation of existing Pacific Gas and Electric Company (PG&E) electrical infrastructure within the project area. As previously presented to the Board on December 12, 2023 (File No. 23-1338), the project includes seven PG&E transmission towers, as well as distribution facilities that may be affected by implementation of the restoration project. At that time, the Board approved allocation of $200,000 from Cannabis Tax revenues for the PG&E engineering deposit needed to advance the project.

PG&E has now provided an updated Engineering Advance request dated August 6, 2026. PG&E anticipates that the first $200,000 Engineering Advance (EA) will fund preliminary modeling and limited design development for modifications to seven transmission towers, likely advancing the design to no more than approximately 30 percent. PG&E has advised that additional Engineering Advances, currently estimated at approximately $400,000 to $800,000, may be required to complete the engineering phase; these amounts remain preliminary and will be refined as PG&E develops the scope of work. PG&E currently estimates the overall tower-modification portion of the project at approximately $3.5 million to $7.0 million.

PG&E cannot begin the preliminary engineering work until it receives the signed Engineering Advance letter and the $200,000 deposit. Once the relo...

Click here for full text