MEMORANDUM
TO: Board of Supervisors
FROM: Scott De Leon, Public Works Director
DATE: January 30, 2019
SUBJECT: Approve Plans and Specifications for the Clark Drive Pavement Repair Project; Bid No. 18-24, Federal Aid Project No. BRLS-5914 (025)
EXECUTIVE SUMMARY:
The Plans and Specifications for the Clark Drive Pavement Repair Project are complete and a copy has been filed with the Clerk of the Board.
The construction estimate is approximately $275,000. The Federal Highway Administration (FHWA) and Caltrans offer Federal Highway Bridge Program (HBP) funds to eligible projects. The project is 100% funded for construction with Federal Highway Bridge Program funds.
Note: To minimize reproduction costs, the original documents are attached to the Clerk’s copy of the original cover memo and only a copy of this memo is furnished to each individual board member
FISCAL IMPACT: __ None _X_Budgeted __Non-Budgeted
Estimated Cost: 275,000
Amount Budgeted:
Additional Requested:
Annual Cost (if planned for future years):
FISCAL IMPACT (Narrative):
The construction estimate is approximately $275,000. The Federal Highway Administration (FHWA) and Caltrans offer Federal Highway Bridge Program (HBP) funds to eligible projects. The project is 100% funded for construction with Federal Highway Bridge Program funds.
STAFFING IMPACT (if applicable):
Recommended Action
RECOMMENDED ACTION:
Staff recommends that the Board of Supervisors approve the Plans and Specifications and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids