Memorandum

Date: November 10, 2026

To: The Honorable Brad Rasmussen, Chair, Lake County Board of Supervisors

From: Robin Borre, Special Districts Administrator

Subject: Adopt Resolution authorizing and designating Special Districts Administrator, or authorized designee, to sign and submit a funding agreement and any amendments for funding under the State Water Resources Control Board for the upgrades to the Southeast Wastewater Collection System Project.

Executive Summary:

The County of Lake was allocated $2,500,000 in Assembly Bill 113 (Budget Act of 2026, Chapter 248, Statutes of 2026), signed by the Governor on September 18 of 2026, to be administered by the State Water Resources Control Board for upgrades to the Southeast Wastewater Collection System in Clearlake, in response to the Robin Lane sewage spill.
The funding was facilitated by Senator Mike McGuire. These funds have been made available after months of co-advocacy from Lake County Special Districts Administrator, Robin Borre (and staff, including Allen Miller, Lori Baca and Chris Becker), County Administrative Officer, Susan Parker, Assistant County Administrative Officer, Stephen Carter, and Chief Deputy County Administrative Officer and Legislative Coordinator, Matthew Rothstein, Brad Rasmussen, Chair of the Lake County Board of Supervisors, and District 2 Supervisor, Bruno Sabatier.
The funds will be used to advance approved Capital Improvement Projects in the Southeast system. These projects include the Southeast Treatment Plant Headworks Upgrades and Pipe Relocations, Southeast Dump Station Construction, Southeast Treatment Plant – Headworks Mechanical Screen projects and if funding is remaining the design of the Southeast Treatment – Vallejo Lift Station.
The Headworks project is already in pre-liminary design and will include separation of the three force main pipes coming into the headworks. The pipes from Lift Station #1 (the 10” and 16”) will remain in the existing headworks. Th...