MEMORANDUM
TO: Board of Supervisors
FROM: Scott De Leon, Public Works Director
DATE: May 2, 2017
SUBJECT: Consideration of Approval of Contract Change Order No. One for Mathews Road at Manning Creek Bridge Replacement Project, Federal project No. BRLO-5914(072); Bid No. 16-02 for an increase of $1,897.75 and a revised contract amount of $1,221,696.95; and authorize the Chair to sign.
EXECUTIVE SUMMARY: Attached for the Board’s review and approval is Contract Change Order (CCO) 1 for the subject project. Contract Change Order No. 1 addresses adjusting all contract items to final in-place quantities. This change resulted in an increase of $1,897.75 to the original contract amount of $1,220,798.90 for a new contract amount of $1,221,696.95.
FISCAL IMPACT: _X_ None __Budgeted __Non-Budgeted
Estimated Cost: 1897.75
Amount Budgeted:
Additional Requested:
Annual Cost (if planned for future years):
FISCAL IMPACT (Narrative): This project is fully funded by the Federal Highway Administration (FHWA) thru Federal Highway Bridge Program (HBP) funds and California Toll Credit funds. Therefore, this project is 100% federally and state funded thru construction.
STAFFING IMPACT (if applicable): None
Recommended Action
RECOMMENDED ACTION: Staff recommends the Board approve Contract Change Order No. One for Mathews Road at Manning Creek Bridge Replacement Project, Federal project No. BRLO-5914(072); Bid No. 16-02 for an increase of $1,897.75 and a revised contract amount of $1,221,696.95; and authorize the Chair to sign.