Title
Body
MEMORANDUM
TO: Board of Supervisors
FROM: Scott Harter, Deputy Administrator
Jan Coppinger, Administrator
DATE: February 6, 2018
SUBJECT: Adopt Resolution accepting the CSA-7 & CSA-18 Water System Repair Project as complete and authorize the CSA-7 & CSA-18 Administrator to sign the Notice of Completion
EXECUTIVE SUMMARY: The contract for the construction of the subject project, as authorized under the Agreement dated October 18, 2016 was satisfactorily completed on October 27, 2017. Staff is working on close out paper work related to the project, however the physical work is completed and ready to be accepted on behalf of the Districts. The attached Resolution authorizing the signature of the Administrator on the Notice of Completion has been prepared for your consideration.
FISCAL IMPACT: _X_ None __Budgeted __Non-Budgeted
Estimated Cost: n/a
Amount Budgeted: n/a
Additional Requested:
Annual Cost (if planned for future years):
FISCAL IMPACT (Narrative): n/a
STAFFING IMPACT (if applicable): n/a
RECOMMENDED ACTION: Adopt Resolution accepting the CSA-7 & CSA-18 Water System Repair Project as complete and authorize the CSA-7 & CSA-18 Administrator to sign the Notice of Completion