MEMORANDUM

 

TO:                                           Board of Supervisors

FROM                     Scott De Leon, Public Works Director

DATE                     February 13, 2018

SUBJECT                     Adopt Resolution Approving Right-of-Way Certification for East Lake Elementary Safe Routes to School and CDBG Project - Federal Aid No. SR2SL-5914 (064), SRTSL-5914 (057) and SRTSL-5914 (097)

 

EXECUTIVE SUMMARY:  Caltrans requires certification on all State funded projects that Right-of-Way is cleared before they will allow the project to proceed to the next phase.  All Right-of-Way for this project is now clear and ready to proceed with the certification.

Caltrans also requires that this Right-of-Way certification be authorized by an adopted resolution by the Board of Supervisors. 

On September 13, 2016, the Board adopted Resolution 2016-141, approving a Right-of-Way Certification for this project.  Since it has been more than a year between the Right-of-Way certification and start of construction, Caltrans is requiring the County of Lake to re-certify the Right-of-Way.  A new Certification and resolution have been prepared in compliance with Caltrans’ directive. Both documents are attached for your consideration. 

FISCAL IMPACT:                      _X_ None __Budgeted __Non-Budgeted

                                                               Estimated Cost:

                                                               Amount Budgeted:

                                                               Additional Requested:

                                                               Annual Cost (if planned for future years):

 

FISCAL IMPACT (Narrative): None

 

STAFFING IMPACT (if applicable): None

 

Recommended Action

RECOMMENDED ACTION:  Adopt Resolution Approving Right-of-Way Certification for East Lake Elementary Safe Routes to School and CDBG Project - Federal Aid No. SR2SL-5914 (064), SRTSL-5914 (057) and SRTSL-5914 (097)