File #: 18-704    Version: 1 Name:
Type: Agreement Status: Agenda Ready
File created: 8/10/2018 In control: Lake County Watershed Protection District
On agenda: 8/21/2018 Final action:
Title: (Sitting as the Lake County Watershed Protection District, Board of Directors) Award of Bid No. WR 18-01 for Levee Patrol Road Gravel Repair Project, Upper Lake, CA. in the amount of $62,884 and authorize the Water Resources Director to execute the Agreement and Notice of Award
Sponsors: Lake County Watershed Protection District
Attachments: 1. Agreement WR 18-01, 2. Bid Tabulation WR 18-01, 3. Award Notice WR 18-01
Title
Body
MEMORANDUM

TO: Board of Directors, Lake County Watershed Protection District
FROM: David Cowan, Water Resources Director
DATE: August 21, 2018
SUBJECT: (Sitting as the Lake County Watershed Protection District, Board of Directors) Award of Bid No. WR 18-01 for Levee Patrol Road Gravel Repair Project, Upper Lake, CA. in the amount of $62,884 and authorize the Water Resources Director to execute the Agreement and Notice of Award
EXECUTIVE SUMMARY:

In 2016 your Board adopted resolutions and approved a project agreement between the State of California Department of Water Resources (DWR) and the Lake County Watershed Protection District for Levee Patrol Road Gravel Repair. The scope of the project is the repair of 0.60 miles of levee patrol roads. The agreement with DWR stipulates that work must be completed by December 31, 2018.

Grant funds were made available in June, 2017. However, due to natural disasters and staff turnover in 2017/2018, contractor selection and other preparatory work was begun in May, 2018. On July 16, 2018, the Water Resources Department publicly opened bids for the project. One (1) bid was received from Cats4U, Inc. of Healdsburg, CA. Please refer to the attached bid tabulation.

The project will be paid from Budget Unit 8108 and reimbursed by DWR. In 2016, the cost of the project was anticipated to be $45,639.00. The lone bidder submitted a bid for $62,884.00. DWR management has indicated that they will fund the additional amount and a contract amendment is being drafted. Funding is available in Budget Unit 8108 to cover the additional cost in the event DWR funding is not approved.

The project is 90% funded by the State of California Department of Water Resources with Lake County Water Resources Department providing local match of 10%, or $6,288.40.

FISCAL IMPACT: __ None _x_ Budgeted __Non-Budgeted
Estimated Cost: $62,884.00
Amount Budgeted: $62,884.00
Additional Requested:
Annual Cost (if planned for future...