Title: Approve Plans and Specifications for the Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project; Bid No. 18-11, State Project no.: ATPL-5914(103) and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans
Sponsors: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Body
MEMORANDUM

TO: Board of Supervisors
FROM: Scott De Leon, Public Works Director
DATE: January 29, 2019
SUBJECT: Approve Plans and Specifications for the Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project; Bid No. 18-11, State Project no.: ATPL-5914(103) and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans
EXECUTIVE SUMMARY:
The Plans and Specifications for the Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project are complete and a copy has been filed with the Clerk of the Board.

The construction estimate is approximately $400,000.
The California Transportation Commission (CTC) provides funds to eligible projects through the Active Transportation Program (ATP). Therefore, this project is 100% funded for construction with State funds.
Staff recommends that the Board of Supervisors approve the Plans and Specifications and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans.
Note: To minimize reproduction costs, the original documents are attached to the Clerk's copy of the original cover memo and only a copy of this memo is furnished to each individual board member

FISCAL IMPACT: __ None _X_Budgeted __Non-Budgeted
Estimated Cost: $400,000
Amount Budgeted:
Additional Requested:
Annual Cost (if planned for future years):

FISCAL IMPACT (Narrative): The California Transportation Commission (CTC) provides funds to eligible projects through the Active Transportation Program (ATP). Therefore, this project is 100% funded for construction with State funds.

STAFFING IMPACT (if applicable): None

Recommended Action
RECOMMENDED ACTION:

Approve Plans and Specifications for the Upper Lake Pedestrian Improvements for Upper Lake High, Mi...