Title: Approve the Award of Bid for the Cycle 7 & Cycle 8 Signs and Striping Project, Bid No. 18-22, Federal Aid Project No.'s HSIPL-5914(104) & HSIPL-5914(113) to McGuire Pacific Constructor's, of Auburn CA in the Amount of $1,239,526 and Authorize the Chair to execute the Notice of Award and Agreement
Sponsors: Public Works
Attachments: 1. Bid Tab, 2. NoticeofAward, 3. Sample Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Body

MEMORANDUM

 

TO:                                          Board of Supervisors                     

FROM:                     Scott De Leon, Public Works Director

DATE:                                          March 12, 2019

SUBJECT:                     Approve the Award of Bid for the Cycle 7 & Cycle 8 Signs and Striping Project, Bid No. 18-22, Federal Aid Project No.'s HSIPL-5914(104) & HSIPL-5914(113) to McGuire Pacific Constructor's, of Auburn CA in the Amount of $1,239,526 and Authorize the Chair to execute the Notice of Award and Agreement

 

EXECUTIVE SUMMARY:

The Purchasing Department publicly opened bids for the subject project on Thursday, January 31, 2019.  Two (2) bids were received and the lowest responsible bidder was McGuire Pacific Constructor’s, of Auburn, CA. Please refer to the attached bid tabulation.

The project is fully funded from Highway Safety Improvement Program (HSIP) funds.

The scope of the project is to upgrade the warning signs, delineators and traffic striping on various roads in Lake County.

Staff recommends that the Board of Supervisors award the Contract for the Cycle 7 & Cycle 8 HSIP Signs and Striping Project to McGuire Pacific Constructor’s in the amount of $1,239,526.00 and authorize the Chair to execute the Agreement and execute the attached Notice of Award.

 

FISCAL IMPACT:                      __ None _X_Budgeted __Non-Budgeted

                                                               Estimated Cost: 1,239,526.00

                                                               Amount Budgeted: 1,239,526.00

                                                               Additional Requested:

                                                               Annual Cost (if planned for future years):

 

FISCAL IMPACT (Narrative):

The project is fully funded from Highway Safety Improvement Program (HSIP) funds.

 

 

STAFFING IMPACT (if applicable):

 

Recommended Action

RECOMMENDED ACTION: