File #: 19-444    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 4/30/2019 In control: BOARD OF SUPERVISORS
On agenda: 5/14/2019 Final action:
Title: Adopt Resolution Delegating to the County Public Works Director the Ministerial Authority to obtain certain temporary construction easements up to $10,000 required for Clayton Creek Road at Clayton Creek Bridge Replacement Project
Sponsors: Public Works
Attachments: 1. Resolution1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Body
MEMORANDUM

TO: Board of Supervisors
FROM: Scott De Leon, Public Works Director
DATE: May 14, 2019
SUBJECT: Adopt Resolution Delegating to the County Public Works Director the Ministerial Authority to obtain certain temporary construction easements up to $10,000 required for Clayton Creek Road at Clayton Creek Bridge Replacement Project

EXECUTIVE SUMMARY:
On February 28, 2017, the County of Lake entered into an agreement with Quincy Engineering to provide preliminary and final design, environmental services, right of way, bidding, and construction assistance services in order to replace the Clayton Creek Bridge at Clayton Creek Road (14C-0031) in Lake County, CA.
The Clayton Creek Bridge on Clayton Creek Road is slated for construction in 2020, pending the availability of federal funds. In order to obtain the required temporary construction easements for the project, authorization must be provided to the County's consultant, Quincy Engineering, to proceed. The assessor's parcel numbers for the affected parcels are APNs 012-044-070, 012-030-060, and 012-044-09-00.
This project is 100% funded for construction with state and federal funds. The Federal Highway Administration (FHWA) and Caltrans offer Federal Highway Bridge Program (HBP) funds and California Toll Credits to eligible projects. The FHWA, in an agreement with Caltrans, provides for the use of toll credits in lieu of local matching funds.
Recommendation
Staff recommends that the Board of Supervisors approve the resolution delegating to the County Public Works Director the ministerial authority to obtain temporary construction easements from certain parcels (APNs 012-044-070, 012-030-060, and 012-044-09-00) and authorize the Chair to sign said resolution.
FISCAL IMPACT: X__ None __Budgeted __Non-Budgeted
Estimated Cost:
Amount Budgeted:
Additional Requested:
Annual Cost (if planned for future years):

FISCAL IMPACT (Narrative):
This project is 100% funded for construction wit...