File #: 19-682    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 7/1/2019 In control: BOARD OF SUPERVISORS
On agenda: 7/16/2019 Final action:
Title: Consideration of Change Order No. One for Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project, State Project No. ATPL-5914(103); Bid No. 18-11, for a Decrease of $6,000 and a Revised Contract amount of $405,328.09, and authorize the Chair to sign
Sponsors: Public Works
Attachments: 1. Bid No 18-11 CCO1
Title
Body
MEMORANDUM

TO: Board of Supervisors
FROM: Scott De Leon, Public Works Director
DATE: July 9, 2019
SUBJECT: Consideration of Change Order No. One for Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project, State Project No. ATPL-5914(103); Bid No. 18-11, for a Decrease of $6,000 and a Revised Contract amount of $405,328.09, and authorize the Chair to sign
EXECUTIVE SUMMARY:
Attached for the Board's review and approval is Contract Change Order (CCO) 1 for the subject project.
Contract Change Order No. 1 addresses the contractors request to be allowed to place concrete curb, gutter & sidewalk monolithically. This results in a decrease of $6,000.00 to the contract amount of $411,328.09 for a revised contract amount of $405,328.09.
This project is fully funded from the State's Active Transportation Program (ATP) funds. Therefore, this project is 100% state funded thru construction.
RECOMMENDATION
Staff recommends approval of Change Order No. One for Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project, State Project No. ATPL-5914(103); Bid No. 18-11, for a Decrease of $6,000 and a Revised Contract amount of $405,328.09, and authorize the Chair to sign.

FISCAL IMPACT: __ None _X_ Budgeted __Non-Budgeted
Original contract amount: $411,328.09
Total amount of all change orders (including this one): (-$6,000)
Percentage of total change orders amount to initial contract amount:

Amount Budgeted: $416,000.00


FISCAL IMPACT (Narrative):
This project is fully funded from the State's Active Transportation Program (ATP) funds. Therefore, this project is 100% state funded thru construction.

STAFFING IMPACT (if applicable):

Recommended Action
RECOMMENDED ACTION:
Staff recommends approval of Change Order No. One for Upper Lake Pedestrian Improvements for Upper Lake High, Middle & Elementary Schools Project, State Project No. ATPL-5914(103); Bid No. 18-11, for a Decrease...