MEMORANDUM
TO: Board of Directors
FROM: Jan Coppinger, Special Districts Administrator
DATE: October 8, 2019
SUBJECT: Adopt Resolution Accepting the Anderson Springs Sewer Collection System Project, Contract #4364 as Complete and Authorize the Special Districts Administrator to Sign and Record the Notice of Completion.
EXECUTIVE SUMMARY:
On 11/7/2017 a contract was awarded to K.J.Woods for the installation of a sewer collection system within the Anderson Springs Community. On September 18, 2019 the project was completed.
Attached for consideration is a Resolution which would accept the work as complete on behalf of the District and authorize the Special Districts Administrator to sign and record the Notice of Completion.
FISCAL IMPACT: _X_ None __Budgeted __Non-Budgeted
Estimated Cost:
Amount Budgeted:
Additional Requested:
Annual Cost (if planned for future years):
FISCAL IMPACT (Narrative): None
STAFFING IMPACT (if applicable): None
Recommended Action
RECOMMENDED ACTION:
Adopt the Resolution accepting the Anderson Springs Sewer Collection System Project #4364 as complete and authorize the Special Districts Administrator to sign the Notice of Completion.