Memorandum


Date: January 28, 2020

To: The Honorable Moke Simon, Chair, Lake County Board of Supervisors

From: Scott De Leon, Public Works Director

Subject: Approve Plans and Specifications for the Bartlett Springs Road at Cache Creek Bridge Replacement Project; Bid No. 20-01, Federal Project No: BRLO-5914(092)

Executive Summary: (include fiscal and staffing impact narrative):
The Plans and Specifications for the Bartlett Springs Road at Cache Creek Bridge Rehabilitation Project are complete and a copy has been filed with the Clerk of the Board.

The construction estimate is approximately $1,011,000.

The California Department of Transportation (Caltrans) provides funds to eligible projects through the Highway Bridge Program (HBP). Therefore, this project is 100% funded for construction with Federal funds.

Staff recommends that the Board of Supervisors approve the Plans and Specifications and authorize the Public Works Director / Assistant Purchasing Agent to advertise for bids once authorization to proceed with construction phase is received from Caltrans.

Note: To minimize reproduction costs, the original documents are attached to the Clerk's copy of the original cover memo and only a copy of this memo is furnished to each individual board member

If not budgeted, fill in the blanks below only:
Estimated Cost: $1,011,000.00 Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply): ? Not applicable
? Well-being of Residents ? Public Safety ? Infrastructure ? Technology Upgrades
? Economic Development ? Disaster Recovery ? County Workforce ? Revenue Generation
? Community Collaboration ? Business Process Efficiency ? Clear Lake ? Cost Savings
If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:
Which exemp...

Click here for full text