File #: 20-198    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 3/6/2020 In control: BOARD OF SUPERVISORS
On agenda: 4/7/2020 Final action:
Title: Consideration of Change Order No. 3 with Coleman Environmental Engineering, Inc. for FEMA FMAG Culvert Replacement No. 1 & No. 2, Federal Project No.'s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R, Bid No. 19-01, For an increase of $2,540.94 and a Revised Contract amount of $647,841.27
Sponsors: Public Works
Attachments: 1. Change Order 3, Bid No 19-01

Memorandum

 

 

Date:                                          April 7, 2020

 

To:                                          The Honorable Moke Simon, Chair, Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

                     

Subject:                     Consideration of Change Order No. 3 with Coleman Environmental Engineering, Inc. for FEMA FMAG Culvert Replacement No. 1 & No. 2, Federal Project No.'s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R, Bid No. 19-01, For an increase of $2,540.94 and a Revised Contract amount of $647,841.27

 

Executive Summary: (include fiscal and staffing impact narrative):

Attached for the Board’s review and approval is Contract Change Order (CCO) 3 for the subject project. 

 

Contract Change Order No. 3, Site 10 - Castlewood Road, addresses increasing the structure excavation and slurry-cement backfill bid items to reflect actual in-place quantities and the need for extra work to remove a portion of large boulders encountered in the excavation during installation of the concrete headwalls.

 

This results in an increase of $2,540.94 to the contract amount of $645,300.33 for a revised contract amount of $647,841.27.

 

This project is funded 75% from the State’s CalOES funds and a 25% local match. Therefore, this project is 100% funded thru construction.

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action: Staff recommends approval by the Board of Supervisors of CCO 3 and that the Board authorize the Chair to execute said CCO for an increase of $2,540.94 and a revised contract amount of $647,841.27.