File #: 20-438    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/6/2020 In control: BOARD OF SUPERVISORS
On agenda: 5/19/2020 Final action:
Title: Approve the Plans and Specifications for the Hill Road Correctional Facility Phase II Roof Project, Bid No. 20-17, and authorize the Public Services Director / Assistant Purchasing Agent to advertise for bids.
Sponsors: Public Services
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Memorandum


Date: May 19, 2020

To: The Honorable Moke Simon, Chair, Lake County Board of Supervisors

From: Lars Ewing, Public Services Director

Subject: Approve the Plans and Specifications for the Hill Road Correctional Facility Phase II Roof Project, Bid No. 20-17, and authorize the Public Services Director / Assistant Purchasing Agent to advertise for bids

Executive Summary:
The plans and specifications for the Hill Road Correctional Facility Phase II Roof Project are complete.

The estimate of probable construction costs is approximately $650,000. Sufficient funding for the project is included in the FY 19-20 Capital Projects Budget Unit 1778.

The plans and specifications are available at the Public Services office for Board of Supervisors' review.

FISCAL IMPACT: __ None _X_Budgeted __Non-Budgeted
Estimated Cost: $650,000
Amount Budgeted: $650,000
Additional Requested: -
Annual Cost (if planned for future years): -

FISCAL IMPACT (Narrative): $2 million was included in the FY 19-20 budget for both the jail phase 2 roof and the courthouse roof. Once contract costs for both projects are determined the excess funds can then be reallocated.

STAFFING IMPACT (if applicable): N/A

If not budgeted, fill in the blanks below only:
Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply): ? Not applicable
? Well-being of Residents ? Public Safety ? Infrastructure ? Technology Upgrades
? Economic Development ? Disaster Recovery ? County Workforce ? Revenue Generation
? Community Collaboration ? Business Process Efficiency ? Clear Lake ? Cost Savings
If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:
Which exemption is being requested?
How long has Agreement been in place?
...

Click here for full text