File #: 20-494    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/20/2020 In control: BOARD OF SUPERVISORS
On agenda: 6/2/2020 Final action:
Title: Approve Award of Bid for the Clayton Creek Road at Clayton Creek Bridge Replacement Project, Bid No. 20-10; Federal Aid Project No. BRLO-5914(077) and Authorize the Chair to Sign
Sponsors: Public Works
Attachments: 1. Bid Tab Bid No 20-10, 2. NOA Bid No 20-10, 3. draft agree Bid 20-10
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          June 2, 2020                     

 

To:                                          The Honorable Moke Simon, Chair, Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

                     

Subject:                     Approval of Award of Bid for the Clayton Creek Road at Clayton Creek Bridge Replacement Project, Bid No. 20-10; Federal Aid Project No. BRLO-5914(077) and Authorize the Chair to Sign

 

Executive Summary: (include fiscal and staffing impact narrative):

The Purchasing Department publicly opened bids for the subject project on Thursday, April 30, 2020.  Seven (7) bids were received and the apparent lowest responsible bidder was West Coast Contractors DBA Oregon West Coast Contractors, of Coos Bay, OR. Please refer to the attached bid tabulation.

 

The project is fully funded from the Federal Highway Bridge Program (HBP) and Toll Credits. The scope of the project is the replacement of the Clayton Creek Road Bridge over Clayton Creek near Lower Lake, CA.

 

Staff recommends that the Board of Supervisors award the Contract for the Clayton Creek Road at Clayton Creek Bridge Replacement Project to West Coast Contractors DBA Oregon West Coast Contractors in the amount of $1,613,171.40 and authorize the Chair to execute the Agreement and execute the attached Notice of Award.                                            

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action:

Award Contract for the Clayton Creek Road at Clayton Creek Bridge Replacement Project to West Coast Contractors DBA Oregon West Coast Contractors in the amount of $1,613,171.40 and authorize the Chair to execute the Agreement and execute the attached Notice of Award.