Date:                                           July 28, 2020                                                               

 

To:                                          The Honorable Moke Simon, Chair, Lake County Sanitation District Board of Directors

 

From:                                          Jan Coppinger, Special Districts Administrator                     

                     

Subject:                     (Sitting as Lake County Sanitation District) Consideration of Change Order #1 with Mercer Fraser Company for Anderson Springs Sewer Project, for an increase of $23,688.00 and a revised contract amount of $1,950,683.00 and Authorize Board Chair to Execute

 

Executive Summary: (include fiscal and staffing impact narrative):

Attached for review and approval is Change Order #1 for the Anderson Springs Sewer Project - Onsite Work. This contract was to install and connect the wet well and grinder pumps at each property. Every property was different and each presented its own set of challenges. Some properties required additional work or materials to accomplish the connection.

 

There are eleven changes making up the total change order of $23,688.

 

Item No. 1

Installation of additional 4-inch Schedule 80 PVC gravity sewer piping beyond the contract

quantity of 12 feet as directed in the field and at the previously agreed to unit price of $15.00

per linear foot. Full compensation to be at the agreed Lump Sum price of: $6,060.00

 

Item No. 2

Installation of additional 1-1/4” electrical conduit and longer pump cables including exchange of

75 foot long pump supply cable with 100 foot long pump supply cable at the agreed to unit

price of $105.24 per installation as indicated in Signa Mechanical Quotation Number Q901480.

Longer pump cables were installed at Plan ID #16, #29, #54, #71 and #88. Work generally

includes, but is not limited to trenching; conduit; fittings; bedding; backfilling; compaction; pump

cable installation; and delay.

Full compensation to be at the agreed Lump Sum price of: $526.20

 

Item No. 3

Abandon and fill existing septic tank at Plan ID#73 on 2/4/2020 and 2/5/2020 as indicated in

Extra Work Bill 1.0. Work generally includes, but is not limited to excavation for septic tank

pumping (by others); creating holes in bottom of septic tank, excavation and demolition of

existing septic tank lid and sidewalls; furnish and install pea gravel in septic tank; backfilling;

compaction; and delay.

Full compensation to be at the agreed Force Account price of: $2,727.18

 

Item No. 4

Additional time and labor to identify and address failing septic tank at Plan ID#38 on 2/18/2020

and 2/19/2020 as indicated in Extra Work Bills 2.0 and 4.0, respectively. Work generally

includes, but is not limited to utility potholing, excavation for septic tank pumping (by others);

coordination with Lake County Health Department, trenching in close proximity of buildings,

demolition of concrete, and delay.

Full compensation to be at the agreed Force Account price of: $2,909.13

 

Item No. 5

Removal and replacement of existing water service at Plan ID#34 on 2/18/2020 as indicated in

Extra Work Bill 3.0. Work generally includes, but is not limited to utility potholing; trenching;

furnish and install 3/4" water service piping and fittings; bedding; backfilling; compaction; and

delay. Full compensation to be at the agreed Force Account price of: $436.75

 

Item No. 6

Additional time and labor to hand excavate electrical conduit trench from control panel to wet

well at Plan ID#29 on 2/28/2020 as indicated in Extra Work Bill 5.0. Work generally includes,

but is not limited to utility hand trenching; hand backfilling; compaction; and delay.

Full compensation to be at the agreed Force Account price of: $1,187.22

 

Item No. 7

Abandon and fill existing septic tank at Plan ID#30 on 3/23/2020, 3/25/2020 and 3/31/2020 as

indicated in Extra Work Bills 6.0, 7.0 and 8.0, respectively. Work generally includes, but is not

limited to utility potholing; excavation for septic tank pumping (by others); creating holes in

bottom of septic tank, excavation and demolition of existing septic tank lid and sidewalls;

furnish and install pea gravel in septic tank; backfilling; compaction; and delay.

Full compensation to be at the agreed Force Account price of: $3,152.74

 

Item No. 8

Additional work due to septic tank conflict at Plan ID#24 on 4/6/2020 as indicated in Extra

Work Bill 9.0. Work generally includes, but is not limited to utility potholing; hand excavation

around existing septic tank; additional trench; removal and replacement of existing private

property gravity sewer plumbing; backfilling; compaction; and delay.

Full compensation to be at the agreed Force Account price of: $1,033.92

 

Item No. 9

Additional work due to unforeseen conflict with pressurized leach field at Plan ID#1 on

4/7/2020 as indicated in Extra Work Bill 10.0. Work generally includes, but is not limited to

utility potholing; hand excavation; repair of damaged private property pressurized leach field

lines; backfilling; compaction; and delay.

Full compensation to be at the agreed Force Account price of: $672.34

 

Item No. 10

Additional time and labor to hand excavate electrical conduit trench from control panel to wet

well, gravity sewer trench, and pressure lateral trench at Plan ID#23 on 4/16/2020 as indicated

in Extra Work Bill 11.0. Work generally includes, but is not limited to utility hand trenching;

hand backfilling; compaction; removal and replacement of block retaining wall; and delay.

Full compensation to be at the agreed Force Account price of: $2,794.05

 

Item No. 11

Additional time and labor to hand excavate electrical conduit trench from control panel to wet

well, gravity sewer trench, and pressure lateral trench at Plan ID#7 on 4/21/2020 and

4/22/2020 as indicated in Extra Work Bills 12.0 and 13.0, respectively. Work generally

includes, but is not limited to utility hand trenching; hand backfilling; compaction; removal and

replacement of landscape retaining wall; and delay.

Full compensation to be at the agreed Force Account price of: $2,188.47

 

This project is funded with DCBG Grant funds and this change order falls within the amount allocated for this project.                                                

 

If not budgeted, fill in the blanks below only:

Estimated Cost: _$23,688.00__ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 