File #: 21-98    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 2/24/2021 In control: BOARD OF SUPERVISORS
On agenda: 3/9/2021 Final action:
Title: Consideration of Change Order No. 1 for Lampson Field Airport Runway 10-28 Asphalt Slurry Seal Rehabilitation AIP No. 3-06-0117-019-2018, Bid No. 19-11 for a decrease of $15,892.89 and a revised contract amount of $989,817.11.
Sponsors: Public Works
Attachments: 1. CCO#1 Bid19-11

Memorandum

 

 

Date:                                          February 24, 2021

 

To:                                          The Honorable Bruno Sabatier, Chair, Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

                     

Subject:                     Consideration of Change Order No. 1 for Lampson Field Airport Runway 10-28 Asphalt Slurry Seal Rehabilitation AIP No. 3-06-0117-019-2018, Bid No. 19-11 for a decrease of $15,892.89 and a revised contract amount of $989,817.11.

 

Executive Summary: (include fiscal and staffing impact narrative):

 

Attached for the Board’s review and approval is Contract Change Order (CCO) 1 for the subject project. 

 

CCO 1 addresses the need to compensate the contractor for additional materials and labor to repair unstable subgrade soils encountered in Area Repair #10 and balances all contract items to final in-place quantities.

 

The results of this CCO 1 is a decrease of $15,892.89 to the original contract amount of $1,005,710.00 for a revised contract amount of $989,817.11.

 

This project is 90% funded by a Federal Aviation Administration (FAA) grant, 5% State match, and 5% Local match. Therefore, this project is 100% funded thru construction.

 

RECOMMENDATION

 

Staff recommends approval by the Board of Supervisors of CCO 1 and that the Board authorize the Chair to execute said CCO for a decrease of $15,892.89 and a revised contract amount of $989,817.11.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                      

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action:

Staff recommends approval by the Board of Supervisors of CCO 1 and that the Board authorize the Chair to execute said CCO for a decrease of $15,892.89 and a revised contract amount of $989,817.11.