File #: 21-329    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 4/20/2021 In control: BOARD OF SUPERVISORS
On agenda: 5/4/2021 Final action:
Title: Consideration of Contract Change Order No. 1 with Storesund Construction, Inc. for the Soda Bay CSA-20 Redwood Water Tanks Replacement Project, CalOES Disaster #4240 and Project Number 4240-40-36R, for an increase of $30,055.09 and a revised contract amount of $655,139.54.
Sponsors: Special Districts
Attachments: 1. CCO_01 - signed.pdf

Memorandum

 

 

Date:                                          May 4, 2021                     

 

To:                                          The Honorable Bruno Sabatier, Chair, Lake County Board of Supervisors on Behalf of CSA-20, Soda Bay

 

From:                                          Scott Harter, Special Districts Administrator

                     

Subject:                     Consideration of Contract Change Order No. 1 with Storesund Construction, Inc. for the Soda Bay CSA-20 Redwood Water Tanks Replacement Project, CalOES Disaster #4240 and Project Number 4240-40-36R, for an increase of $30,055.09 and a revised contract amount of $655,139.54.

 

Executive Summary: (include fiscal and staffing impact narrative):

Attached for the Board’s review is Contract Change Order #1 for the subject project.  Contract Change Order (CCO) #1 addresses changes related to unsuitable subgrade conditions discovered during excavation and preparation of the foundations for the two new bolted steel tanks.  There were unanticipated areas of weak soil under the former tanks which required additional excavation followed by the placement and compaction of suitable material. 

A field order was given to proceed with the remediation work on a T&M basis.  Work was performed by the contractor resulting in an increased cost of $30,055.09.  This CCO proposes to formalize that field direction and increase the contract by the $30,055.09 resulting in a revised contract amount of $655,139.54.

This contract is funded by a FEMA/CalOES Hazard Mitigation Grant Program grant at a 75% grant/25% local match ratio.  This CCO will not result in an increase beyond the approved grant amount.

                                                     

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action:  Staff recommends approval by the Board of Supervisors on behalf of CSA-20 Soda Bay of CCO #1 and that the Board authorize the Chair to execute CCO #1 for an increase of $30,055.09 and a revised contract amount of $655,139.54.