File #: 21-360    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 4/23/2021 In control: BOARD OF SUPERVISORS
On agenda: 5/11/2021 Final action:
Title: Adopt Resolution Authorizing the Public Works Director to Sign the Notice of Completion for the FEMA FMAG Culvert Replacement No. 1 & No. 2 Project; Federal Project No.’s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R; Bid No. 19-01
Sponsors: Public Works
Attachments: 1. NOC-FMag, 2. Res-FMag
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          April 26, 2021                     

 

To:                                          The Honorable Bruno Sabatier, Chair, Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Worker I/II

                     

Subject:                     Approve the Resolution Authorizing the Public Works Director to Sign the Notice of Completion for the FEMA FMAG Culvert Replacement No. 1 & No. 2 Project; Federal Project No.’s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R; Bid No. 19-01

 

Executive Summary: (include fiscal and staffing impact narrative):

 

On August 6, 2019, the Board approved an Agreement with Coleman Environmental Engineering, Inc. for the FEMA FMAG Culvert Replacement No. 1 & No. 2 Project. The work under this Agreement was satisfactorily completed on October 27, 2020.

 

Staff has prepared a resolution authorizing the Public Works Director to sign the Notice of Completion.

 

Staff recommends that the Board of Supervisors approve the Resolution Authorizing the Public Works Director to Sign the Notice of Completion for the FEMA FMAG Culvert Replacement No. 1 & No. 2 Project; Federal Project No.’s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R; Bid No. 19-01, and authorize the Chairman to execute said Resolution

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                      

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 and/or Fiscal Crisis Management Plan (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Infrastructure                                           Technology Upgrades

Economic Development                                           Disaster Recovery                                           County Workforce                      Revenue Generation

Community Collaboration                      Business Process Efficiency                      Clear Lake                                           Cost Savings                                          

If request for exemption from competitive bid in accordance with County Code Chapter 2 Sec. 2-38, fill in blanks below:

Which exemption is being requested?

How long has Agreement been in place? 

When was purchase last rebid?

Reason for request to waive bid?

 

Recommended Action:

Staff recommends that the Board of Supervisors approve the Resolution Authorizing the Public Works Director to Sign the Notice of Completion for the FEMA FMAG Culvert Replacement No. 1 & No. 2 Project; Federal Project No.’s FMAG DR 5093-1-1R & FMAG DR 5112-1-1R; Bid No. 19-01, and authorize the Chairman to execute said Resolution