File #: 22-513    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 5/16/2022 In control: Planning Commission
On agenda: 5/26/2022 Final action:
Title: 9:10 a.m. Public Hearing on Consideration of Major Use Permit UP 22-09 and that a determination has been made that this project required a Mitigated Negative Declaration to consider the adoption of an Initial Study IS 22-11. The applicant, NEW CINGULAR WIRELESS PCS, DBA AT&T MOBILITY – to consider to allow a 150’ tall lattice cell tower and support equipment within a 40’ x 45’ enclosed lease area. The proposed project is located at 16200 E. Highway 20, Clearlake Oaks, CA; APN: 010-020-29, and further described as APN: 010-020-29.
Sponsors: Community Development
Attachments: 1. Attachment 1 Vicinity Map, 2. Attachment 2 site, access, grading plans, 3. Attachment 3 agency comments, 4. Attachment 4 COAs, 5. Attachment 5 IS, 6. Attachment 6 photo sims, 7. Attachment 7 EMT ltr of support, 8. Attachment 8 Staff Report, 9. Public Comment (Thorburn), 10. Public Comment (Thorburn) #2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

(
'
ITEM #2
May 26, 2022
9:10 AM
April 8, 2021
STAFF REPORT

TO: Planning Commission

FROM: Mary Darby, Community Development Director

Prepared by: Eric Porter, Associate Planner

DATE: May 26, 2022

RE: New Cingular Wireless PCS, dba AT&T Mobility; Major Use Permit (UP 22-09), and Initial Study (IS 22-11)
Location: 16200 E. Highway 20, Clearlake Oaks
APN: 010-020-29.

Supervisor District 3


ATTACHMENTS: 1. Vicinity Map
2. Site Plan, Access, and Grading Plan
3. Agency Comments
4. Proposed Conditions of Approval
5. Initial Study IS 22-11
6. Photo Simulations
7. Letter of Support - Emergency Service Provider

I. EXECUTIVE SUMMARY

The applicant is requesting a major use permit for a new 150' tall cell tower on the subject site, along with an emergency backup generator and associated electrical equipment needed for the cell tower to function. This project is for a new single lattice tower that will be capable of allowing co-located facilities on it. This application includes:

* One (1) 40'x 45' (1,800 sq. ft.) carrier lease area
* One (1) new 150' (Co-locatable) tall lattice cell tower on concrete pads
* Nine (9) panel antennas
* One (1) microwave antenna
* Nineteen (19) remote radio units (RRU's)
* One (1) 8' x 8' walk in closet equipment shelter
* One (1) 30KW emergency backup generator
* One (1) 190-gallon UL142 rated generator fuel tank
* 5.0' x 10.0' generator concrete pad
* One (1) step down transformer on a 4'2" x 4'4" concrete pad
* One (1) 3' x 5' U.G. Telco vault
* Gravel bed throughout enclosure
* Six (6) foot tall chain link fence around the 40' x 45' enclosure
* One (1) 12' wide double gate for enclosure access
* 1,421 feet of underground power and fiber-optic cables in 6' wide utility corridor
* Improve existing access road with 20' ...

Click here for full text