File #: 22-754    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 7/13/2022 In control: BOARD OF SUPERVISORS
On agenda: 7/26/2022 Final action:
Title: Approve Amendment Two to Agreement between the County of Lake and Quincy Engineering, Inc. for Engineering Services for Hill Road MP 7.75 Landslide Repair Project, in Lake County, CA in the amount not to exceed $125,000, for a revised total contract amount of $420,805.07 and authorize the chair to sign
Sponsors: Public Works
Attachments: 1. Amend2HillRdMP7.75LandslideRepairQuincy
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Memorandum

 

 

Date:                                          July 26, 2022

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

 

Subject:                     Approve Amendment Two to Agreement between the County of Lake and Quincy Engineering, Inc. for Engineering Services for Hill Road MP 7.75 Landslide Repair Project, in Lake County, CA in the amount not to exceed $125,000, for a revised total contract amount of $420,805.07 and authorize the chair to sign

 

Executive Summary:

 

On May 2, 2017, the Department of Public Works entered into an agreement with Quincy Engineering to provide preliminary and final design, right of way, bidding and construction assistance services for Hill Road MP 7.75 Landslide Repair Project.

 

Exhibit “C” of Amendment Two provides a detail sheet that clearly identifies each affected task, task budget augmentation, task budget reduction, and task budget re-allocation.  Caltrans has concurred with this amendment and associated costs are eligible for reimbursement As a result of this amendment, the contract amount will be increased by a net amount of $125,000.

 

The Federal Highway Administration (FHWA) Emergency Relief Funding Grant provides 100% of the funds required for this project.

 

 

 

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Consistency with Vision 2028 (check all that apply):                                           Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

Staff recommends that the Board of Supervisors approve the Amendment Two to Agreement for Engineering Services for Hill Road MP 7.75 Landslide Repair Project with Quincy Engineering in the amount not to exceed $125,000, for a revised total contract amount of $420,805.07, and authorize the Chairman to execute said Agreement.