File #: 24-98    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 1/24/2024 In control: BOARD OF SUPERVISORS
On agenda: 2/6/2024 Final action:
Title: Approve Change Order No. 2 Middletown Multi-Use Path Improvements Project, State Project No. ATPL – 5914(102) Bid No. 22-05 For A Decrease of $114,481.12 & A Revised Contract Amount of $1,161,688.48.
Sponsors: Public Works
Attachments: 1. CCO#2 Bid No.22-05

Memorandum

 

 

Date:                                          February 6, 2024

 

To:                                          The Honorable Lake County Board of Supervisors

 

From:                                          Scott De Leon, Public Works Director

 

Subject:                     Approve Change Order No. 2 Middletown Multi-Use Path Improvements Project, State Project No. ATPL - 5914(102)                     Bid No. 22-05 For A Decrease of $114,481.12 & A Revised Contract Amount of $1,161,688.48.

 

Executive Summary:

Attached for the Board’s review and approval is Contract Change Order (CCO) 2 for the subject project. 

 

Contract Change Order No. 2 addresses the need to decrease costs in labor, materials, equipment, subcontractors, and trucking due to reducing the scope of work by eliminating a section of the project.

 

This results in a decrease of $114,459.12 to the contract amount of $1,276,149.60 for a revised contract amount of $1,161,690.48.

 

This project is funded 100% from the State’s ATP funds and local funds. Therefore, this project is 100% funded through construction.

 

If not budgeted, fill in the blanks below only:

Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________ 

 

Purchasing Considerations (check all that apply):                                           Not applicable

Fully Article X. <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI>- and/or Consultant Selection Policy <http://lcnet.co.lake.ca.us/Assets/Intranet/Policy/Policies+$!26+Procedures+Manual/Ch4_2021v2.pdf>-Compliant (describe process undertaken in “Executive Summary”)                     

Section 2-38 <https://library.municode.com/ca/lake_county/codes/code_of_ordinances?nodeId=COOR_CH2AD_ARTXPU_S2-38EXCOBI> Exemption from Competitive Bidding (rationale in “Executive Summary,” attach documentation, as needed)                     

For Technology Purchases: Vetted and Supported by the Technology Governance Committee <http://lcnet.co.lake.ca.us/Assets/Intranet/Intranet+Forms/Information+Technology/AdvPlan.pdf> (“Yes,” if checked)

Other (Please describe in Executive Summary)

 

Consistency with Vision 2028 <http://www.lakecountyca.gov/Government/Directory/Administration/Visioning/Vision2028.htm> (check all that apply):                                                                Not applicable

Well-being of Residents                                           Public Safety                                                                Disaster Prevention, Preparedness, Recovery                     

Economic Development                                           Infrastructure                                                                County Workforce                     

Community Collaboration                      Business Process Efficiency                      Clear Lake                                                               

 

Recommended Action: 

Staff recommends approval by the Board of Supervisors of CCO 2 and that the Board authorize the Chair to execute said CCO for a decrease of $114,481.12 and a revised contract amount of $1,161,688.48.