Memorandum
Date: September 17, 2024
To: The Honorable Lake County Board of Supervisors
From: Glen March, Public Works Director
Subject: Consideration of Change Order No. 3, Middletown Multi-Use Path Improvements Project, State Project No. ATPL - 5914(102), Bid No. 22-05 for an increase of $247,258.81, and amended contract amount of $1,408,959.29.
Executive Summary:
Staff requests the County of Lake (County) Board of Supervisors (Board) to approve Contract Change Order No. 3 3 in the amount of $247,258.81 for a total contract amount of $1,408,959.29, for the Middletown Multi-Use Path Improvements Project and authorize the Chair to execute the Change Order.
On May 23, 2022, the Board awarded the construction contract for the Project, in the amount of $1,117,449.60 to Argonaut Constructors and authorized the Chair to execute the agreement.
On October 24, 2023, the Board approved Contract Change Order No. 1 in the amount of $158,700.00 which increased the contract amount to $1,276,149.60 and authorized the Chair to execute the change order.
On February 6, 2024, the Board approved contractor change order no. 2, in the amount of -$114,481.12, which reduced the contract amount to $1,161,690.48, and authorized the Chair to execute the contract change order.
Additional asphalt concrete, paid at the contract unit rate, was incorporated into the work and design/construction modifications were required to complete the work, which totaled the contract change order amount of $247,258.81.
Contract Change Order No. 3 in the amount of $247,258.81, will increase the contract amount to $1,408,959.29.
This project is funded from the State's ATP funds, ARPA funds and local funds. Therefore, this project is 100% funded through construction.
If not budgeted, fill in the blanks below only:
Estimated Cost: ________ Amount Budgeted: ________ Additional Requested: ________ Future Annual Cost: ________
Purchasing Considerations (check all that apply): ? Not applicable
?...
Click here for full text