File #: 17-794    Version: 1 Name:
Type: Agreement Status: Agenda Ready
File created: 8/31/2017 In control: BOARD OF SUPERVISORS
On agenda: 9/12/2017 Final action:
Title: Approve Amendment One to Agreement between the County of Lake and Quincy Engineering, Inc. for Construction Management Services for Replacement of Anderson Creek Bridge at Foard Road (14C-0076 and Dry Creek Bridge at Dry Creek Road (14C-0070) in Lake County, California in the amount not to exceed $368,594.56, and Authorize the Chair to Sign.
Sponsors: Public Works
Attachments: 1. Amendment One
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Body
MEMORANDUM

TO: Board of Supervisors
FROM: Scott DeLeon, Public Works Director
DATE: September 12, 2017
SUBJECT: Approve Amendment One to Agreement between the County of Lake and Quincy Engineering, Inc. for Construction Management Services for Replacement of Anderson Creek Bridge at Foard Road (14C-0076 and Dry Creek Bridge at Dry Creek Road (14C-0070) in Lake County, California in the amount not to exceed $368,594.56, and Authorize the Chair to Sign.

EXECUTIVE SUMMARY: On June 28, 2016, the Department of Public Works entered into an Agreement with Quincy Engineering, Inc. for Construction Management Services for Replacement of Anderson Creek Bridge at Foard Road (14C-0076) and Dry Creek Bridge at Dry Creek Road (14C-0070) in Lake County, CA.
Additional effort was needed in order to meet the construction schedule, facilitate contractor's activities, and address project-related issues. Consequently, construction of both bridges has been successfully accomplished and all project-related issues have been resolved.
This amendment will provide for the additional effort required for Task 2, "Construction Field Inspection and Management" and Task 6, "Post Construction Services". This amendment also captures efficiencies in completing other tasks thru re-allocation of the remaining task budgets. Caltrans has concurred with this amendment and associated costs are eligible for reimbursement. As a result of this amendment, the contract amount will be increased as indicated below:

Summary by Bridge Amendment One Fee Not to Exceed
Anderson Creek Bridge at Foard Road $3,390.68 $185,344.73
Dry Creek Bridge and Dry Creek Road $23,694.16 $183,249.83

Totals $27,084.84 $368,594.56

This project is 100% funded for construction with state and federal funds. The Federal Highway Administration (FHWA) and Caltrans offer Federal Highway Bridge Program (HBP) funds and California Toll Credit funds to eligible project...

Click here for full text